PROJECT 1 - Thirsk Lake
-
Setup de-watering to maintain clean water flow to creek
-
Setup silt control and temporary sediment ponds
-
Install new trash racks and grates at bottom of dam
-
Install 600mm bypass pipe in channel bottom
-
Clean brush and debris
-
Install concrete tilt-up building over 600mm flotus valve
-
Install inspection and cleaning port in 600mm steel line